Request for Proposals: Middle School Interior Remodel
Project Location: Pagosa Peak Open School
Issue Date: April 8, 2026
Proposal Due Date: May 15, 2026
Construction Start Date: June 13, 2026
Project Completion Deadline: August 8, 2026
Project Overview
Pagosa Peak Open School is seeking bids from licensed and bonded General Contractors to oversee a minor interior remodel of our middle school wing. The primary goal is to replace existing temporary curtain partitions with permanent, non-weight-bearing walls to create dedicated classroom environments.
Scope of Work
The selected General Contractor will be responsible for the management of this project, including:
- Framing & Drywall: Construction of non-structural interior walls as per provided floor plans.
- Electrical: Coordination and oversight of electrical subcontractors to install outlets, switches, and lighting adjustments within new walls.
- Fire Suppression: Direct coordination with Cooper Fire to ensure the existing sprinkler system is adjusted and certified according to the new layout.
- Finishing: Taping, mudding, texture, and painting to match existing school aesthetics.
Exclusions: No structural, mechanical (HVAC), or plumbing work is required forĀ
this project.
Management Responsibilities
The GC will act as the primary point of contact and project lead. Responsibilities include:
- Subcontractor Oversight: Sourcing (if not already selected), scheduling, and supervising all trades.
- Financial Administration: Reviewing and signing off on all subcontractor invoices prior to submission to the school for payment.
- Permitting & Compliance: Ensuring all work meets local building codes and fire safety regulations.
- Timeline Adherence: Maintaining a rigorous schedule to ensure a hard completion date of August 8, 2026.
Submission Requirements: Interested contractors should submit a proposal including:
- Company Profile: Proof of licensure, insurance and bonding ability.
- Experience: Brief summary or resume listing similar projects.
- Proposed Timeline: A high-level schedule showing how the deadline will be met.
- Cost Proposal: A comprehensive bid including management fees and estimated subcontractor costs (or a fixed-price bid).
Evaluation Criteria
Proposals will be evaluated based on the contractor’s ability to meet the summer deadline, their experience,, and their overall project management approach.
Key Dates & Bidding Timeline:
Mandatory Pre-Bid Walkthrough: April 30, 2026
Deadline for Questions: May 7, 2026
Bid Submission Date: May 15, 2026 by noon
Project Award Date: May 18, 2026
Final Completion Date: August 8, 2026
Bids must be submitted in a sealed envelope clearly marked ‘Middle School Remodel Bid’ and delivered to the Pagosa Peak Open School School Front Office no later than May 15 at 12:00 p.m., and bids will be opened and read aloud at Pagosa Peak Open School in the Conference Room at 12 p.m. the same day.